The signal every POC omits.

Published: 2026-06-18

URL: https://samonai.substack.com/p/your-pilot-isnt-a-pilot-without-kill


Minimalist editorial illustration: a navy semicircular gauge with a single amber needle pointing toward a clearly marked amber threshold notch, beyond which the arc shifts to muted slate.

Your pilot isn't a pilot without kill criteria

A pilot without predefined kill criteria is not a pilot. It is a demo with budget.

That distinction sounds like semantics. It isn't. It's the difference between a project that can end cleanly and one that will only end when something else forces it to — a budget cut, an executive reshuffle, a public failure. The majority of enterprise AI POCs in 2026 fall into the second category. They can't be killed because nobody defined what dead looks like.

NIST's AI Risk Management Framework is explicit on this point. The MANAGE function requires documented rollback triggers and predefined conditions under which a system is taken out of production. The framework has been public since January 2023 and updated through 2024. Three years later, the median enterprise POC still has none of this written down.

That's not a compliance gap. It's a project-definition gap, and it's why the cancellation numbers look the way they do.

What a pilot is supposed to do

A pilot has one job: produce a falsifiable answer to the question "should this become a production system." If the answer is yes, you scale it. If the answer is no, you shut it down and write the learning memo.

Either outcome is useful. Both require the same prerequisite: you have to have named, before the pilot started, what evidence would produce each answer. If the evidence for "no" doesn't exist — if there's no condition under which the pilot would fail — then the pilot is not answering a question. It's executing a plan to ship.

This is the move that quietly happens in most enterprise programs. A "pilot" is launched with a launch date for production already scheduled. The reviews are framed as checkpoints, not decision points. The team is staffed with people whose incentives are tied to shipping, not to deciding. The pilot and the rollout are the same project wearing two labels.

That's fine if the project is small and reversible. It's a failure mode if the project is large and load-bearing. And the AI program portfolios of most enterprises are now large and load-bearing.

What kill criteria actually look like

A kill criterion is a measurable condition, defined before the pilot starts, whose occurrence within a specified timeframe ends the project. It has four properties.

Measurable. A number you can calculate, not a judgment call. "The system makes too many mistakes" is not a kill criterion. "End-to-end task success rate below 72% on the pilot eval set after four weeks of tuning" is.

Time-bound. It has to resolve within a defined window — typically a quarter. Open-ended kill criteria don't kill. They defer.

Pre-committed. Written down, signed off by the exec sponsor, and attached to the pilot charter before the work begins. Kill criteria written after the pilot has been running for two quarters are not kill criteria; they're face-saving exit ramps.

Non-negotiable. If the condition triggers, the project ends. Not "enters a remediation phase." Not "gets a new PM." Ends. It can be restarted later, with new assumptions and a new spec. But the current pilot is over.

Most enterprise pilots fail at least two of these four tests, usually three. The "kill criteria" section of the project charter, when it exists at all, contains phrases like "if the system is not meeting expectations" or "pending stakeholder review," which are not criteria. They are procedures for avoiding a criterion.

Why teams don't write them

The engineering team usually knows how to write these. Ask a senior engineer what would make them recommend shutting down a system and you'll get a specific, measurable answer. The gap is organizational.

Kill criteria create audit trails. A written criterion is a commitment. If the system triggers the criterion and the project doesn't end, there's now a documented case of the organization ignoring its own governance. That's a risk the exec sponsor often prefers not to take. Ambiguous criteria let you live in both worlds — you can claim governance exists without being accountable to it.

Sunk-cost momentum. Once a pilot has been running for six months, a clear kill criterion is the political equivalent of asking the sponsor to admit they misallocated capital. The organization prefers narratives like "it's evolving" or "we're pivoting the scope." These are kill criteria avoided via vocabulary.

Vendor incentives. If the system is vendor-provided, the vendor's team is deeply incentivized against any criterion that could end the contract. Vendor-friendly kill criteria get negotiated into meaninglessness during the procurement phase — "pending mutual review," "based on continuous improvement," "subject to the MSA renewal terms."

The wrong owner. Kill criteria written by the team running the pilot are an obvious conflict of interest. They need to be written with the exec sponsor and the governance function in the loop, and ratified by someone whose incentives are not aligned with the pilot's continuation.

These are solvable problems, but they require treating kill criteria as a first-class artifact, not a box to check on the charter template.

A minimal template

If your organization doesn't have a template for this, use the one below. It takes about two hours to fill out and it's the governance artifact most likely to change the outcome of the pilot.

System purpose. One sentence describing what the pilot is trying to answer.

Decision owner. The named individual who will make the go/no-go call at the end of the pilot. Must be senior enough to actually kill the project. Cannot be the project lead.

Decision date. Hard date by which the decision must be made. Not a range. Not "Q2."

Success criteria. Two or three measurable conditions whose joint satisfaction leads to a scale decision. Include a number, a method of measurement, and a data source for each.

Kill criteria. Two or three measurable conditions whose occurrence leads to shutdown. Same structure: number, measurement method, data source.

What's out of scope. Conditions that look bad but are explicitly not part of the decision — known issues the team has decided to ignore for this pilot, edge cases deferred to a future pilot. This protects against scope-creep kills and good-faith kills for the wrong reason.

Rollback plan. What happens to the pilot's artifacts, data, and integrations if the kill criteria trigger. This is the part NIST cares about and most teams forget. A pilot you can't actually turn off is a production system with informal governance.

That's the whole template. One page. The hardest row to fill is "decision owner," and if you can't name one, you've discovered something more important than any technical finding the pilot would have produced.

The test that actually works

The simplest test for whether an AI project in your organization is a real pilot: walk into the sponsor's office and ask them, in one sentence, what would end this project this quarter.

If they answer with a specific, measurable condition, you have a pilot.

If they answer with a process — "we'd review it with the steering committee" — you have a demo with budget.

If they don't answer, you have a permanent expense with a launch date.

The second and third categories are what the cancellation-rate research is measuring. Gartner, BCG, and MIT NANDA are not observing technology failures. They are observing project definitions that made success legible and failure invisible. That math resolves the way it was always going to resolve, just slowly, as each project burns through its capital allowance and gets shelved without a clean postmortem.

Your next pilot is either designed to answer a question or designed to survive the year. The kill criteria tell you which one.


For your most-funded AI initiative, what measurable condition would end it this quarter?

— Sam